Readiness Drive Cycle Procedure
WARNING: This page is about a different car, the 2014 Volkswagen Passat, 2013 Volkswagen Passat, and 2012 Volkswagen Passat. However, it is still accessible from the selected car via links, so may be relevant.
-- CONNECT: Scan Tool.
-- During the individual test steps, the vehicle needs to be in normal mode, except during service regeneration.
NOTE:
For automatic transmission use the manual gear selection mode, if available for the following steps.
| Step | Procedure | Result / Action to Take |
|---|---|---|
| 1 | Misfire Monitoring:
|
|
| 2 | PM Filter Monitoring:
|
|
| 3 | EGR System Monitoring:
|
|
| 4 | NMHC Catalyst Monitoring:
|
|
| 5 | NOx/SCR After-treatment (Regeneration) Monitoring:
|
|
| 6 | Exhaust Gas Sensor Monitoring:
|
|
| 7 | Boost Pressure System Monitoring:
|
|
NOTE:
Depending on the scan tool used. The readiness code status may be displayed as complete, passed or OK. At an exterior temperature < 7°C, the setting of the readiness for the NOx catalytic converter test is delayed, here the vehicle must be Driven considerably longer.