Home >> Volkswagen >> 2009 >> Rabbit 2D Hatchback, 2.5 B, Standard >> Repair and Diagnosis >> Engine Performance >> System >> 2.5L - Generic Scan Tool - Engine Code(S): CBTA & CBUA >> St Generic Scan Tool >> Diagnosis And Testing >> Diagnostic Procedures >> Secondary Air Injection Pump Relay, Checking
April 5, 2026: LEMON Manuals is launched! Read the announcement.

Secondary Air Injection Pump Relay, Checking

Special Tools And Workshop Equipment Required 

Test Requirements 

Test Procedure 

-- Perform a preliminary check to verify the customers complaint. Refer to PRELIMINARY CHECK .

Start Diagnosis 

-- Remove the Secondary Air Injection (AIR) Pump Relay -J299-.

Checking voltage

-- Remove the Secondary Air Injection (AIR) Pump Relay -J299-.

-- Using a Multimeter, check the Secondary Air Injection (AIR) Pump Relay -J299- socket 1 (relay terminal 30) to Ground (GND).

Specified value: battery voltage.

If the specified value was Not obtained:

-- Check the wiring connection from the Secondary Air Injection (AIR) Pump Relay -J299- socket 1 (relay terminal 30) to the Battery -- (+) terminal for an open circuit or high resistance.

-- Check the wiring connections for damage, corrosion, loose or broken terminals.

-- If necessary, repair the faulty wiring connection.

If the specified value was obtained:

-- Install the Secondary Air Injection (AIR) Pump Relay -J299-.

Start the engine.

-- Using a multimeter, check the Secondary Air Injection (AIR) Pump Relay -J299- socket 2 (relay terminal 87) to ground.

Specified Value: Battery Voltage. 

-- Switch the ignition off.

If the specified value was Not obtained:

-- Check the circuit from the Secondary Air Injection (AIR) Pump Relay -J299- socket 2 (relay terminal 87) through fuse 27 in Fuse Box B, out to the Secondary Air Injection (AIR) Pump Motor -V101- connector, terminal 2 for an open circuit or a short circuit to Ground (GND).

-- Check the wiring connections for damage, corrosion, loose or broken terminals.

-- If necessary, repair the faulty wiring connection and replace fuse if blown.

If the specified value was obtained:

Checking wiring

If the manufacturers test box is being used, perform the following step.

-- Install the test box.

If the manufacturers test box is not being used, perform the following step.

-- Remove the Engine Control Module (ECM) -J623-. Refer to the Repair Information.

-- Using a multimeter, check the Secondary Air Injection (AIR) Pump Relay -J299- socket 4 (relay terminal 85) to the Engine Control Module (ECM) -J623- electrical harness connector T94 terminal 94 for resistance.

Secondary Air Injection (AIR) Pump Relay -J299- socket/terminal Engine Control Module (ECM) -J623- electrical connector T94 terminal or test box socket
4/85 94

Specified Value: 1.5 Ω Max. 

If the specified value was Not obtained:

-- Check the wiring for an open circuit, a short circuit to each other, Battery (+), and Ground (GND).

-- Check the electrical harness connector for damage, corrosion, loose or broken terminals.

-- If necessary, repair the faulty wiring connection.

If no malfunction is found in the wiring and voltage supply was OK:

-- Replace the Secondary Air Injection (AIR) Pump Relay -J299-.

-- Erase the DTC memory.

-- Perform a road test to verify repair.

Final Procedures 

After repair work, the following work steps must be performed in the following sequence:

  1. Check the DTC memory. Refer to DIAGNOSTIC MODE 03 - READ DTC MEMORY .
  2. If necessary, erase the DTC memory. Refer to DIAGNOSTIC MODE 04 - ERASE DTC MEMORY .
  3. If the DTC memory was erased, generate readiness code. Refer to READINESS CODE .