Generator Inspection: Rotor

WARNING: This page is about a different car, the 2010 Suzuki Kizashi. However, it is still accessible from the selected car via links, so may be relevant.
  1. Using ohmmeter (1), check for continuity between slip rings (2) of rotor. If there is no continuity, replace rotor.

    Standard resistance between slip rings of rotor 

    1.7 - 2.1 Ω 

    Fig 1: Checking Continuity Between Slip Rings Of Rotor
    G06528331Courtesy of SUZUKI OF AMERICA CORP.
  2. Using ohmmeter (1), check that there is no continuity between slip ring (2) and rotor core (3). If there is continuity, replace rotor.
    Fig 2: Checking Continuity Between Slip Ring And Rotor Core
    G06528332Courtesy of SUZUKI OF AMERICA CORP.
  3. Check slip rings and rotor fan surface for roughness or scoring. If roughness or scoring is discovered, replace rotor.