Cylinder-to-Front Head O-Ring Removal and Installation: Installation

WARNING: This page is about a different car, the 2005 Suzuki Reno and 2005 Suzuki Forenza. However, it is still accessible from the selected car via links, so may be relevant.
  1. Rest the rear head on the support block J-35372. Locate the control valve at the 6 o'clock position.
  2. Install cylinder alignment rod J-34993 through the 11 o'clock and the 5 o'clock bolt holes.
  3. Lubricate the new cylinder-to-compressor housing O-ring with clean polyalkaline glycol (PAG) oil.
  4. Install the new O-ring in the cylinder O-ring groove.
  5. Install the thrust washer and bearing in the same order as they were removed.
  6. Align the guide pin recess in the compressor housing with the guide pin. Press down on the compressor housing with both hands to force it over the O-ring on the cylinder assembly.
  7. Add a new through-bolt gasket to the through-bolts and install it into the compressor assembly. Four through-bolts must thread into the rear head before removing the guide pins.

    Tighten 

    Alternately tighten the through-bolts in progressive torque sequence to 10 N.m (89 lb-in).

  8. Install a new shaft seal. Refer to "SHAFT SEAL REPLACEMENT :".
  9. Add new PAG oil equal to the amount drained in Step  3.
  10. Install the clutch coil. Refer to "CLUTCH COIL REMOVAL AND INSTALLATION :".
  11. Install the clutch rotor and bearing. Refer to "CLUTCH ROTOR AND BEARING DISASSEMBLY AND INSTALLATION :".
  12. Install the clutch plate and hub assembly. Refer to "CLUTCH PLATE AND HUB ASSEMBLY DISASSEMBLY AND ASSEMBLY :".
  13. Perform a leak test on the compressor. Refer to "LEAK TESTING REFRIGERANT SYSTEM :".
  14. Install the compressor. Refer to "COMPRESSOR REMOVAL AND INSTALLATION :".
  15. Evacuate and recharge the A/C system. Refer to "DISCHARGING, ADDING OIL, EVACUATING, AND CHARGING PROCEDURES FOR A/C SYSTEM :".
    Fig 1: Installing O-Ring In Cylinder O-Ring Groove
    G04104177Courtesy of SUZUKI OF AMERICA CORP.