Using regulated DC power supply

WARNING: This page is about a different car, the 2004 Suzuki Aerio, 2003 Suzuki Aerio, and 2002 Suzuki Aerio. However, it is still accessible from the selected car via links, so may be relevant.
  1. Connect pressure control solenoid valve (1) with regulated DC power supply (2) as shown in the figure.
  2. Turn regulated DC power supply switch ON and increase voltage of power supply keeping current within 1.0 A.
  3. Check for gradual movement of valve (3) in the direction of arrow "A" as voltage is increased.
  4. Check movement of valve (3) in the direction of arrow "B" as voltage is decreased.
  5. Turn power supply switch OFF.
CAUTION: Do not pass current 1.0 A or more, or pressure control solenoid is burned out.
Fig 1: Checking Pressure Control Solenoid Valve Operation (Using Regulated DC)
G00764586Courtesy of SUZUKI OF AMERICA CORP.