Main Shaft Disassembly
- After removing needle bearing for input shaft at the front end of main shaft, pull out high speed sleeve from its hub (3) and remove 3 synchronizer keys.
- Remove circlip in front of hub (3) and pull off hub (3) with special tool, then take out synchronizer springs.
Special tool
(A): 09913-61510
- Remove 3rd synchronizer ring (2), 3rd gear (1) and needle bearing.NOTE: High speed sleeve-hub assembly, synchronizer ring and 3rd gear (1) can be removed all at once by using puller and hydraulic press.
- Remove circlip in the rear part of main shaft (1) and pull off rear bearing (2) with bearing puller (3) and press.
- Remove thrust washer and steel ball and then remove 5th gear, synchronizer ring and needle bearing.
- Pull out reverse sleeve from its hub (2) and remove 3 synchronizer keys.
- Remove circlip and pull off reverse hub (2) from main shaft (1) with bearing puller (3) and press, then take out synchronizer springs.NOTE: It is also possible to remove reverse sleeve-hub as assembly and reverse gear all at once by using puller and press, after removing circlip.
- Remove main shaft reverse gear and needle bearing by hand.
- Using bearing puller (4) and press, remove reverse gear bush (2) and bearing washer (3) from main shaft (1).NOTE: During above work, watch out for steel ball which will come out from inside of washer so as not to lose it.CAUTION: Do not attempt to pull out bearing, washer (3) and bush (2) all together at once. Steel ball would stop bearing and cause damage to it.
- Pull off bearing (1) with bearing puller (2) and press.
- Remove the following in that order: bearing washer, steel ball, low gear, low synchronizer, needle bearing and low gear bush (1).
- Using bearing puller (4) and press, pull out low speed sleeve and hub assembly (2), 2nd gear (3) and 2nd synchronizer ring all together.NOTE: If bush can't be pulled out by hand at Step 11), pull off sleeve and hub together by using press.
- Remove sleeve from hub and then take off synchronizer keys and springs.