TCS Off Switch Inspection
- Remove the TCS OFF switch. (See
TCS OFF SWITCH REMOVAL/INSTALLATION ).
- Verify that the resistance between the TCS OFF switch terminals B and C is as indicated in the table.
- If not as indicated in the table, replace the TCS OFF switch.
TCS OFF SWITCH SPECIFICATION
| Terminal |
Test condition |
Resistance (ohms) |
| B-C |
Switch pressed |
0 |
| Switch released |
1139.99-1163.01 |
- Apply battery voltage to TCS OFF switch terminal J, and connect terminal I to ground.
- Verify that the LED illuminates.