Switch Up & Switch Down Test
- Connect a jumper wire between Violet lead and switch "UP"
terminal. Connect a second jumper wire between switch ground terminal
and "DOWN" terminal. This will test up operation of switch.
- If motor runs, voltage is present to motor. Connect switch to
multiple connector and operate switch. If motor fails to run, replace
switch. Test all switches in this manner.
- To test down operation of switch, connect first jumper wire
between Violet lead and switch "DOWN" terminal, and second jumper wire
between switch ground terminal and "UP" terminal. Repeat tests on all