Work Procedure (After Replace Control Valve)

  1. PERFORM OIL LEVEL CHECK

    G-20 With CONSULT

    1. Select "Work Support" in "TRANSMISSION".
    2. Perform "Oil level check".

    GO TO STEP 2  .

  2. PERFORM NORMALIZATION AND ADAPTATION

    G-20 With CONSULT

    1. Select "Work Support" in "TRANSMISSION".
    2. Perform "Normalization and adaptation".

    WORK END