Ignition Control (Service Information)
>>
CAPACITOR, Ignition
>>
Installation
>>
2.0, 2.4L
July 1:
So it begins
. Don't worry, this is not in the correct legal jurisdiction!
2.0, 2.4L
Fig 1: Removing/Installing Ignition Capacitor - 2.0L/2.4L
Courtesy of CHRYSLER LLC
Install ignition coil capacitor (2) and bolt (3), tighten bolt to 10 N.m (88.5 ft. lbs.).
Connect electrical connector (1).